Pai Kyone, 23 March
With the aim of ensuring swift flow of commodity of rural people and boosting their living standard, the construction works of concrete road have been implemented on Padauk Road in ward-2 in Pai Kyone Sub-Township, Hpa-an district in Kayin State and now, it was completed 100 percent.
The road measuring 920 ft. in length, 16 ft. in width and six inches in thickness was constructed with Ks. 31.60 million of township Development committee’s allotted funds in 2021-2022 FY.
Construction works of the concrete road began on 19 February this year and now it was completed 100 percent. The road will benefit local people in the Township.—Naw Khu(IPRD)
Translated by JT