Sagaing 19 March

A new 66/11 kV 20 MVA transformer is being installed near No.3 inter-district road in Sagaing and it is nearly 50 percent complete, according to a source from the regional office of the Electricity Supply Enterprise.

Electricity is being supplied to some wards in Sagaing Industrial Zone and nearby areas through three transformers. Installation of the transformer began on 1 October 2018 by spending Ks. 547.455 million from the regional government’s funds in the fiscal year 2018-2019. The project is expected to be finished in May.

Upon completion of installing the transformer, sufficient electricity will be distributed to not only factories and workshops in the industrial zone but also some wards and villages.—Win Oo (Zeyar Taing)