Gyobingauk 2 December
Rural electrification project undertaken in Kangyi village in Gyobingauk Township, Tharawady District, Bago Region has been completed by hundred percent and a total of 70 households in the village were distributed electricity starting from November 27, according to Township Department of Rural Development.
The electrification project was conducted with K 10 million funded by VDP and K 8.7 million contributed by public starting from March 16. In the village, there are about 109 households and out of which, 70 households were provided electricity.
Rural electrification projects undertaken in five villages in the township during 2019-2020 FY have been completed by hundred percent and it will bring socioeconomic development of local residents.
Zeyar Tun (Gyobingauk)
Translated by Suyee