Mindat, 3 July
    

Chairman of Mindat District Management Committee U Maung Htoo and committee members made a field trip to constriction site of a two-storey reinforced concrete facility for medical staff in the compound of a public hospital in Mindat Township, Chin State this morning.
    

The structure is being built by a private construction company by spending K 200 million allotted in the current fiscal year. “The estimated cost form the staff housing is K 449 million and the facility is current being built at a cost of K 200 million. The project as a whole is over 65 percent completed,” said a construction official. 
    

Construction of the staff housing commenced on February 7 and the district management committee chairman called site officials for timely completion ahead of schedule.


Salai Aung (IPRD)
Translated by Kyaw Htike Soe